The short answer
A typical kitchen installation takes 1 to 3 weeks — around 1 to 2 weeks for a straightforward like-for-like fit, and 2 to 3 weeks or more where there is plastering, structural work or a new layout. The fit itself is only part of the story: lead times on units and worktops (especially templated quartz or granite) can add weeks before work starts. Knocking through for open-plan adds more again. See the what to expect guide for the day-by-day.
“How long will my kitchen take?” is one of the first questions homeowners ask, and the honest answer is “it depends.” This guide gives realistic 2026 timeframes, a typical day-by-day sequence, and the factors that speed a fit up or slow it down.
Timeline at a glance
- Like-for-like fit 1–2 weeks
- New layout / plastering 2–3 weeks
- Open-plan / structural 3 weeks+
- Worktop template gap often 1–2 weeks
- Unit lead times add weeks before start
- Plan around no kitchen for the duration
A typical day-by-day timeline
A standard fit follows a logical sequence: strip out, first-fix services, units, worktops, then second-fix and finishing. The biggest pause is usually the worktop — templated stone is measured only once the units are in, then cut off-site and fitted days later. The table below shows a typical sequence; your fitter will adapt it to your job.
| Stage | Typical timing | What happens |
|---|---|---|
| Strip out | Day 1 | Remove old kitchen, dispose |
| First fix | Days 1–3 | Plumbing, electrics, plastering |
| Fit units | Days 3–6 | Cabinets levelled and fixed |
| Worktop template & fit | Days 6–12 | Measure, then fit after cutting |
| Second fix & finish | Days 10–15 | Appliances, splashback, snagging |
What makes a fit quicker or slower
A like-for-like swap in the same layout, keeping the plumbing and electrics where they are, is the quickest job. It slows down when the layout changes (new plumbing and circuits), the walls need plastering, the floor needs levelling, or there is structural work such as knocking through. Templated stone worktops add a built-in gap of typically one to two weeks between units going in and the worktop arriving, during which you have units but no work surface.
Living without a kitchen
For the duration of the fit you will be without a usable kitchen, so plan a temporary setup — a microwave, kettle and fridge in another room — and expect dust and disruption. A good fitter will protect floors and routes, but a kitchen fit is messy. Knowing the realistic timeline helps you plan meals, work and family life around it. See what to expect during a fit.
Getting a realistic timeline in your quote
Ask each fitter for a realistic start date and duration in writing, including the worktop template gap, and whether the dates assume units are already delivered. A quote that promises an unrealistically fast turnaround is a warning sign. This is general information; actual timings vary with the scope, the condition of the room, lead times and the trades involved.
Compare kitchen quotes
A realistic timeline is part of a good quote. Compare itemised quotes and schedules from kitchen design and fitting specialists.
Frequently asked questions
How long does a kitchen take to fit?
A typical fit takes 1 to 3 weeks — around 1 to 2 weeks for a straightforward like-for-like job, and 2 to 3 weeks or more where there is plastering, a new layout or structural work. Templated stone worktops add a gap of typically one to two weeks during the fit.
Why is there a wait for the worktop?
Templated stone worktops such as quartz and granite are measured only once the units are in place, then cut off-site to fit precisely, and installed days later. This built-in gap of typically one to two weeks is normal and means you have units but no work surface for a short period.
What slows a kitchen fit down?
Changing the layout (new plumbing and circuits), plastering, levelling the floor, and structural work such as knocking through all add time. Lead times on bespoke units and stone worktops also delay the start, separately from the fit itself.
Will I be without a kitchen the whole time?
Yes — expect to be without a usable kitchen for the duration of the fit. Plan a temporary setup with a microwave, kettle and fridge in another room, and expect dust and disruption while work is underway.
Sources & further reading
- KBSA (Kitchen Bathroom Bedroom Specialists Association) — guidance on installation and scheduling
- GOV.UK / Building Regulations — requirements that affect the work sequence
- TrustMark — finding and checking registered tradespeople
This is general information, not advice for your specific project. Timings vary with scope, room condition, lead times and the trades involved.